System Installation
PNA, Controller, and Test Head Module Interconnections
5. Place the test head module on the work surface in front of the controller.
6. Connect the five cables to the test head module. Details are illustrated in
Figure
3-5. Recommended order of connection:
• +12 V
• R.F. In
• L.O. In
• Ref I.F.
• Test I.F.
7. Torque all cable connections.
Figure 3-5 Details for Test Head Module Connections
8. Apply Velcro fasteners to the ends of the cable sleeve as shown in
For instructions, refer to steps 6 through 8 of the Installation Guide from the Millimeter-wave
Cable Dress kit (document part number N5260-90070 contained in kit part number
N5261-60019).
9. Position the test head module in the approximate location where it will be used for
measurement operation.
10.Connect two cables with 1.85 mm connectors (8121-1233) between the front panel of the
PNA and the test head modules. Details are shown in
3-14
PNA Series Microwave Network Analyzer System
Figure 3-4
Figure 3-2 on page
Installation and Service Guide N5251-90001
N5251A
and
Figure
3-5.