5 Connecting to power supply
Wire assignment, con-
nection cable
24
5.6
Wiring plan - version IP66/IP68 (1 bar)
Fig. 16: Wire assignment in permanently connected connection cable
1
Brown (+) and blue (-) to power supply or to the processing system
2
Shielding
5.7
Switch-on phase
After connecting VEGAFLEX 83 to the bus system, the device first
performs a self-test:
•
Internal check of the electronics
•
Indication of the status message " F 105 Determine measured
value" on the display or PC
•
Status byte goes to fault value
Then the actual measured value is output to the signal cable. The
value takes into account settings that have already been carried out,
e.g. default setting.
1
2
VEGAFLEX 83 • Foundation Fieldbus