9.
Handing over of the installation
Make repeated start attempts to ensure that the adjustments
•
function.
Close the ball valve during operation to check that the gas switch
•
switches off at the set value.
Remove the hose for the air pressure switch to check that the burner
•
locks out.
Check that all protective covers and measurement nipples are
•
mounted and fastened.
Fill out necessary test reports.
•
Instruct the persons in charge of the operation on the service and
•
maintenance of the installation and what to do should any troubles
occur.
Inspection and service must be carried out by authorized personnel.
•
!
Review and service should be performed by authorised
personnel only.
172 615 04-2