Vision REVO User Manual page 102

Lithium battery system
Hide thumbs Also See for REVO:
Table of Contents

Advertisement

Figure 11.1-4 Normal start with junction box
Step 1: Start installing batteries, ensure the battery power cables are correctly connected
and the communications cables have an anti-freeze mechanism. Connect the cables
according to COM1/COM2.
Step 2: Before starting the system, set the DIP codes of CBMS and GBMS. Dip rules have
been put in the manual.
Step 3: Double check the connection of cabinets are corrected
Step 4: Start the cabinets. Check the self-check status of all cabinets when powered on
separately.
SHENZHEN CENTER POWER TECH CO., LTD
Address: Rooms 9-12, 7F, Block B, Building 7, Zone 2, Shenzhen Bay Technological and
Ecological Park, Nanshan District, Shenzhen, China
Tel: 0755-66851118 Fax: 0755-66850678 Email: sales@vision-batt.com
Green Our Earth
Power Your Vision
102