(4) Cable production method
• Peel the sheath (with the length shown below) at both ends of the
cable, and expose the shield braided wire for grounding. (For
grounding with cable clamps. (refer to Section 5.6.3.))
• The cable must be 15m or shorter.
GOT side
130
(5.12)
Within 230
(9.06)
a) For RS-422 cable (AC30/100/300R4-25P)
Refer to (2) (b) 1)
b) For RS-422 cable (User created cable)
Refer to the GOT-A900 series User's Manual (Connection System
Manual) for information about the cable creation method.
• Wind cable shield material around the cable, and pull out the
grounding braided wire of the cable shield material with the length
shown below.
• Pass the grounding braided wire on the programmable logic
controller side through the core.
GOT side
130
(5.12)
Within 150
(5.90)
Grounding braided wire(200mm(7.87inch))
Ferrite Core
(ZCAT3035-1330)
40
(1.57)
Ferrite Core
(ZCAT3035-1330)
Cable shield material
Grounding braided
wire(50mm(1.97inch))
33
Computer link module side side
130
(5.12)
40
Within 400
(15.75)
(1.57)
Computer link module side
130
(5.12)
Within 150
(5.90)
Unit : mm (inch)