SMA Solar Technology AG
6. Loosen all 6 screws of the enclosure lid and remove
the enclosure lid from the front.
7. Verify the absence of voltage L with respect to
N at the AC terminal with an appropriate
measuring device.
☑ If voltage is present, check the installation.
8. Verify the absence of voltage L with respect to PE at
the AC terminal with an appropriate measuring
device.
☑ If voltage is present, check the installation.
☑ The inverter is open and no voltage is present.
Installation Manual
Opening and Closing
SMC46-60A-IA-IEN120471
57