Electrical Connection
Configuration Options
There are 4 different configuration options for the "PowerBalancer" parameter.
Local connection requirements
Select the respective setting and always observe the local connection requirements and
provisions of your grid operator.
• FaultGuard
This operating mode allows for the implementation of a three‑phase line voltage monitoring,
which also reacts to device faults.
– If 1 of the 3 inverters indicates a line voltage fault and stops feeding in,
the other 2 inverters also disconnect from the power distribution grid immediately.
– If 1 of the 3 inverters indicates a device fault and stops feeding in,
the other 2 inverters also disconnect from the power distribution grid 5 minutes later.
38
SMC46-60A-IA-IEN120471
SMA Solar Technology AG
Installation Manual