Chapter 6, Testing the System covers the steps for testing the DDI-11E to confirm
it is functioning properly.
It is recommended that the entire system should be completely tested after the DDI-
11E is installed and placed into service. This test should at a minimum include:
Confirm the DDI-11E and the System 3505 are connected correctly.
Confirm the DDI-11E is connected to the correct phone lines.
Confirming all wire connections are proper and tight.
Confirm the DDI-11E and the System 3505 are communicating properly and
the System 3505 is clear of all trouble messages.
Confirm that dialer panels in the field are communicating properly to the
System 3505.
Confirm that the System 3505 is display the Alarm Messages properly.
Confirm that the redundant systems transfer properly.
Confirm that the DDI can detect a missing phone line.
The User must verify that the System 3505 provides the proper
display of the dialer event. If an automation system is used, proper
operation should be verified at the automation system as well.
700289-0001 Rev. B 10/21

6 Testing the System

6-1

Advertisement

Table of Contents
loading
Need help?

Need help?

Do you have a question about the DDI-11E and is the answer not in the manual?

Table of Contents