iSitePower-M (MAP05A1, MAB05B1)
User Manual
● A surge protection device must be configured for the upstream AC input of the
● The upstream AC input of the system must be configured with an AC circuit
● No leakage protection device is required for the upstream AC input. If a
● A leakage protection device must be configured for the AC output of the
Procedure
Step 1 Connect AC power cables to the terminal connectors.
Figure 7-7 Connecting cables to terminals
Step 2 Install the AC input power cable and secure the cable using cable clips.
Issue 02 (2021-12-30)
NO TICE
system. You need to configure and install the device by yourself.
breaker with a capacity of 40 A. The circuit breaker needs to be configured by
the customer. The D-type tripping circuit breaker cannot be used because it
cannot effectively protect the product.
leakage protection device is configured, it is recommended that the leakage
current be greater than or equal to 100 mA x
power modules.
system. The leakage current must be 30 mA. You need to configure and install
the device by yourself.
Copyright © Huawei Digital Power Technologies Co., Ltd.
7 Electrical Connection
n , where n is the number of