Commissioning
4
Commissioning
4.1
Switching on the measuring device
On completion of the installation (successful post-installation check), wiring (successful
post-connection check) and after making the necessary hardware settings, where applicable, the
permitted power supply (see nameplate) can be switched on for the measuring device.
When the power supply is switched on, the measuring device performs a number of power-up
checks and device self-checks. As this procedure progresses the following messages can appear
on the onsite display:
Display examples:
PROMASS 40
STARTING...
DEVICE SOFTWARE
V XX.XX.XX
SYSTEM OK
→ OPERATION
The measuring device starts operating as soon as the startup procedure is complete.
Various measured values and/or status variables appear on the display.
!
Note!
If an error occurs during startup, this is indicated by an error message.
A complete description of all the error messages → Operating Instructions on the CD-ROM.
12
Æ
Æ
Start-up message
Displays the current software
Beginning of operation
Proline Promass 40
Endress+Hauser
Need help?
Do you have a question about the Proline Promass 40 and is the answer not in the manual?