3.7

INTER CABINET CONNECTIONS

3.7.1 Cabinets positioning and interconnection

NOTE !
The inverter cabinet and rectifier cabinet must be installed on leveled floor.
SG Series 750 & SG Series 750 T12 unit, in standard version, are delivered split into two cabinets.
Align them together with the rectifier cabinet on the right side (cabinet with control panel).
Pay attention, that no loose cables are trapped when pushing the cabinets together.
Inverter cabinet
g
SGS_750_S2_UPS connection cabinets_GE_03US
Detail showing the interconnection of the inverter
and rectifier cabinets. To bolt only on the front side.
Inverter cabinet frame
Once finally positioned, the two cabinets have to be connected together with power and control wiring.
See Section 3.7.2 and 3.7.3.
Modifications reserved
OPM_SGS_ISG_M75_M75_2US_V010.doc
M8 Nut with washer
Fig. 3.7.1-1 Cabinet positioning and interconnection
Rectifier cabinet
Rectifier cabinet frame
Spacer (aluminium)
M8 flat washer
Bolt M8x60
Installation Guide SG Series 750 UL S2 & SG Series 750 T12 UL S2