4.2.4. Mounting Power Cabinet directly on a floor

1.
Drill and tap holes in the floor at the indicated locations (A). The holes must be suitable
for bolts size M16.
2.
Make rectangular holes on the indicated locations (B) and (C). For detailed drawings of
the bottom view of the Power Cabinet see Appendix A Dimensions of the Power Cabinet.
3.
Make sure that the AC power cable and the other cables come out of the floor within the
marked area (B).
4.
Make sure that the DC power cables come out of the floor within the marked areas (C).
5.
For the AC and DC power cable, make sure that a cable length of 1 m is available above
the floor for internal routing inside the cabinet.
6.
For the other cables, make sure that a cable length of 3 m is available above the floor for
internal routing inside the cabinet.
This extra cable length is required to connect the cables to the connectors
inside the Power Cabinet without any problems.
To prevent dust from entering the tapped holes, it is recommended that
you cover them until you are ready to do the placement.
Document: v0.4 / Document No.: TBA | Date: 11-08-2021
HVC-R 100/150 E-Bus Charger Installation Guide
NOTICE
NOTICE
Page 42 of 131

Advertisement

Table of Contents
loading

This manual is also suitable for:

Hvc-r 150

Table of Contents