ABB HVC-R 100 Installation Manual page 95

E-bus charger
Table of Contents

Advertisement

1. Make a loop on the PE wire that is coming from the Power Cabinet or ground electrode
(F).
2. Cut the PE wire from the Power Cabinet or ground electrode to the correct length -
allowing to reach the GND point on the pedestal (I).
3. Loosen and remove the cable gland's (#11 or #12) nut for the PE wire.
4. Route the PE wire from the GND point (I) through the gland to the X8-1 PE connector
block (if the lightning protection is not applied) or X8-2 PE connector block (if lightning
protection is applied) within the Dual Depot Charge Box. See also section Connecting
the PE wire of the AC power cables on Page 68 or Installing lightning protection
(optional) on Page 93. Do not make the wire routing too tight or too loose.
5. Shorten the PE led to the Dual Depot Charge Box to the correct length - allowing to
reach the GND point (I).
6. Tighten the nut of the gland to secure the PE wire.
7. Strip 11 mm of the insulation from the ends of the PE wire inside the Dual Depot
Charge Box.
8. Crimp a ferrule (J) to the end of the PE wire (K).
9. Loosen the connector screw of the PE connector block X8-1 or X8-2.
10. Insert the PE wire into the PE connector block X 8-1 or X8-2.
11. Strip 20 mm of the insulation from the ends of the PE wires (B, F).
12. Attach a wire end ring (G) to the ends of the PE wires (B, F).
13. Place the contact washer (E), both PE wires (B, F) and the toothed washer (D) onto
the GND point (I).
14. Screw the M8 nut (C) onto the GND point (I).
15. Tighten the nut with a tightening torque of 15 Nm.
Document: v0.4 / Document No.: TBA | Date: 11-08-2021
HVC-R 100/150 E-Bus Charger Installation Guide
Page 95 of 131