Installing The San Switch 2/32; Unpack And Verify Carton Contents - HP StorageWorks SAN Switch 2/32 Installation Manual

Version 4.0.x
Hide thumbs Also See for StorageWorks SAN Switch 2/32:
Table of Contents

Advertisement

This chapter covers the following topics:
Carton contents
Installation and safety guidelines
Installing the switch as a stand-alone unit or in an HP 9000 Series Rack
Configuring network addressing
Connecting to the LAN
Connecting an SFP module

Unpack and Verify Carton Contents

Unpack and inspect the SAN Switch 2/32 carton contents as follows.
1. Inspect the shipping container for possible damage caused during transit.
2. Unpack the shipping cartons.
3. Verify that the carton contains the items shown in Figure 2–1 and Table 2–1.
SAN switch 2/32 version 4.0.x installation guide

Installing the SAN Switch 2/32

2
2–1

Advertisement

Table of Contents
loading

Table of Contents