INSTALLATION

WATER MANIFOLD ASSEMBLY

CAUTION
Do not overtighten unions or nuts. Over-
tightening may cause leaks.
CAUTION
Plumbing connections and drains are required
to be in accordance to all State and local
plumbing codes.
A qualified plumber is recommended for providing
1/2" hot and cold supply water lines with shut off
valves to the designated HQT-1 location.
NOTE: Installation instructions are provided with
mixing valve. Mixing valve is factory calibrated to the
low setpoint and will need to be adjusted after
installation. (Retain these instructions for future care
and maintenance of mixing valve.)
1. Connect the water manifold assembly to mixing
valve and secure to wall using a 3/4" (19 mm)
pipe support clamp or conduit clamp. (Clamp is
not provided.) (See Figure 8.)
2. Connect the hot and cold water supply lines to
the appropriate water inlets on the mixing valve.
See OPERATION section for adjusting water
temperature on mixing valve.
Form No. HQTM-0206
O-Ring
Ball Valve
Temperature Gauge
Mixing Valve
Figure 8. Water Manifold Assembly