  Step 1: Activating the System
NOTE
You can use the activation code that appears on the certification
inverter label to activate the inverter in case of a script error or a missing
activation card.
 4. Verify that the inverter is configured to the proper country: Press the LCD light
button until reaching the ID status screen:
I D :               # # # # # # # # # #
D S P 1 / 2 : 1 . 0 2 1 0 / 1 . 0 0 3 4
C P U :
C o u n t r y :
 5. If required, perform the following additional steps before closing the inverter cover:
Country settings or inverter configuration using the internal LCD user buttons –
refer to Country and Grid on page 51.
Communication options connection – refer to Setting Up Communication to the
Monitoring Platform on page 65.
 6. Close the inverter cover by tightening the screws with a torque of 10.3 N*M/ 7.5
lb*ft. For proper sealing, first tighten the corner screws and then the two central
screws. The following figure illustrates recommended order:
 7. Turn ON the DC Safety Unit (if applicable) . If an additional external DC switch is
installed between the power optimizers and the inverter(s) then turn it ON.
A status screen similar to the following appears on the LCD panel:
0 0 0 3 . 1 9 x x
E S P
Figure 17: Tightening order of the screws
Three Phase System MAN-01-00507-4.2