ASSEMBLY INSTRUCTIONS

The TD92 mower is partially assembled as delivered. The mower decks are shipped stacked on steel
legs, all other components are packaged with the main frame. The machine parts list can be used as a
graphical reference for assembly.
1) Remove all strapped components from the main frame assembly.(hose support, rear deck safety
/ cylinder assembly, hitch, transport tires, deck swivels, hardware box).
2) Remove all strapped components from the deck stack (PTO shafts, PTO hanger bearing mount)
3) Raise rear of frame and install transport tires.
4) Raise front of frame and install parking jack.
5) The rear deck safety / cylinder assembly is then installed with the supplied pins. The assembly is
installed on the cylinder mount in the same orientation as packaged. The rod-end of the cylinder
is fastened to the rear-lift mechanism with the lock bar. The cylinder ports facing to the right hand
side of the machine.
6) Connect the pull chain from the deck safety to the rear deck safety. Ensure there are no twists in
chain which can affect operation of the lock release.
7) Install the 90 degree hydraulic adapter in the rod end of the cylinder. The adapter port should
face toward the front of the machine when the cylinder is in the lowered position.
*NOTE - all connections are pipe thread and require thread sealant on all joints at assembly
8) Connect the hydraulic hoses to the rear deck cylinder. The long hose (43") connects the bottom
tee on the wing lock frame to the 90 degree adapter at the rod end of the cylinder. The short
hose (31") is connects the top tee on the wing lock frame to the base end of the cylinder.
9) Unwrap the tractor connection hoses and pull rope. Connect the hydraulic hoses to a hydraulic
power source. Disengage transport lock and cycle the lift cylinders up and down fully 3 or 4 times
to remove all entrapped air from the system. Raise wings to the transport position.
10) Remove red pins in from wing bushings and install deck swivels (grease fitting on pinned joint
should point to the outside of the machine when wings are lowered).
11) The TD92 decks must be lifted from the stand for final assembly.
Ensure proper devices are used to lift deck (approximate deck weight 850lb).
Securely fasten lifting device to deck assembly and ensure deck assembly is
supported by the lifting device before removing fasteners securing deck assembly to
legs.
12) Lift the decks away and install castor wheels as required. Place the mower deck in the
appropriate position at the mower.
13) Using the hydraulic power source, lower the wings / rear lift so that the deck pivot pins can be
installed.
14) Connect wing decks to swivels (pins & fasteners shipped with deck assembly).
15) Install the balance springs to the deck swivels (shipped attached to wing).
16) Install (3) deck PTO shafts. Be sure that the end with no bell shaped guard is attached to the
four-way gear-box (see Page 20).
17) Install intermediate PTO shaft & hanger bearing assembly.
18) Install hose support shield. Make sure that the grease fitting on the hanger bearing is visible
through the hole in the shield for greasing. Run the safety pull rope and hydraulic lines through
the eye of the hose support rod.
19) Install the front hitch with the bolt provided (see Page 19).
20) Grease the intermediate PTO bearing, rear deck lift arms, deck swivels, and check over mower
to find any other spots that missed greasing (All wheels are greased before shipping)
INPUT SHAFT
1) Remove ½" UNC retaining bolt/nut from input shaft.
2) Remove notification tag from intermediate shaft hanger bearing, ensure gold coloured spacer ring
is present against bearing inner race.