13 - STANDARD MAINTENANCE

To ensure optimal efficiency and reliability of the equipment and 
all its functions, we recommend taking out a maintenance contract
with the local organisation set up by your manufacturer.
This contract will include regular inspections by the manufacturer's
Service specialists so that any malfunction is detected and
corrected quickly, ensuring that no serious damage can occur.
The manufacturer's service maintenance contract is the best way
to ensure the maximum operating life for your equipment and,
through  the  expertise  of  manufacturer's  qualified  personnel, 
provides the ideal way to manage your system energy consumption
effectively.
The refrigeration equipment must be serviced by professionals;
however, routine checks may be carried out locally by specially-
trained technicians. See standard EN 378-4.
All refrigerant charging, removal and draining operations must be
carried out by a qualified technician and with the correct equipment 
for the unit. Any inappropriate handling can lead to uncontrolled
fluid or pressure leaks.
IMPORTANT:
Before performing any work on the unit ensure it is
de-energized. If a refrigerant circuit is opened, it must be
evacuated, recharged and tested for leaks. Before any
operation on a refrigerating circuit, it is necessary to evacuate
the refrigerant charge from the device using a load transfer
unit.
Simple preventive maintenance will allow you to get the best
performance from your HVAC unit:
- Optimisation of energy performance,
- Reduced electricity consumption,
- Prevention of accidental component failure,
- Prevention of major time-consuming and costly work,
- Protection of the environment.
There are five maintenance levels for refrigeration units, as defined 
by the AFNOR X60-010 standard.
NOTE: Any deviation from or failure to comply with these
maintenance criteria will render the guarantee conditions for
the refrigeration unit null and void, and will release the
manufacturer from its liability.

13.1 - Level 1 maintenance

These simple procedures can be carried out by the user:
- Visual inspection for oil traces (sign of a refrigerant leak),
- Check for leaks in the circuit (monthly),
- Clean the air-cooled exchanger once a year,
- Check that the protective grilles are present and in good
condition, and that the doors and covers are properly closed,
- Check the alarm report if the unit does not operate (see the 
control manual),
- Verify the refrigerant charge in the liquid line sight glass,
- Verify the temperature difference at the heat exchanger inlet 
and outlet is correct,
- Check for any general signs of deterioration,
- Check the anti-corrosion coatings.

13.2 - Level 2 maintenance

This level requires specific expertise in electrical, hydraulic and 
mechanical systems. It is possible that this expertise may be
available locally; there may be a maintenance service, industrial
site or specialist subcontractor in the area.
The frequency of this maintenance level may be monthly or annual,
depending on the verification type.
In these cases, the following maintenance work is recommended:
Carry out all level 1 operations, then:
Electrical checks (annual checks):
- At least once a year, tighten the electrical connections for the
power circuits (see tightening torques table),
- Check and tighten all control connections, if required,
- Check the labelling of the system and instruments, re-apply
the missing labels if required,
- Remove the dust and clean the interior of the electrical boxes.
Be careful not to blow dust or debris into components;
use a brush and vacuum wherever possible,
- Clean the insulators and bus bar supports (dust combined 
with moisture reduces the insulation gaps and increases
current leakage between phases and from phase to ground),
- Check the presence, condition and operation of electrical
protective devices,
- Check the presence, condition and operation of control
components,
- Check that all heaters are operating correctly,
- Replace the fuses every 3 years or every 15000 hours
(ageing),
- Check that no water has penetrated into the electrical box,
- On the main electrical box and for units equipped with offset 
electrical boxes, regularly check the cleanliness of the filter 
media to maintain the correct air flow.
- Check that the capacitor is operating correctly (Power factor 
correction option).
Mechanical checks:
- Check that the mounting bolts for the ventilation
sub-assemblies, fans, compressors and electrics box are
securely tightened
Hydraulic checks:
- When working on the hydraulic circuit, take care not to
damage the adjacent air-cooled exchanger,
- Check the hydraulic connections,
- Check  the  condition  of  the  expansion  tank  (presence  of 
corrosion or loss of gas pressure) and replace it if required,
- Drain the hydraulic circuit (see chapter "Water flow control 
procedure"),
- Clean  the  water  filter  (see  chapter  "Water  flow  control 
procedure"),
- Replace the gland packing of the pump after 20000 hours of
operation and the bearings after 17500 hours,
- Check the operation of the low water flow safety device,
- Check the condition of pipe thermal insulation,
- Check the concentration of the anti-freeze protection
(ethylene glycol or propylene glycol),
- Check the water flow via the heat exchanger pressure
difference,
- Check  the  condition  of  the  heat-transfer  fluid  or  the  water 
quality,
- Check for corrosion of the steel pipe work.
Refrigerant circuit checks:
- The unit is subject to F-gas tight regulatory checks. Please
refer to the table in the introduction.
- Check the unit operating parameters and compare them with
the previous values,
- Check the operation of the high-pressure switches. Replace
them if there is a fault,
- Check  the  fouling  of  the  dehumidifier  filter.  Replace  it  if 
required,
- Keep and maintain a maintenance sheet, attached to each
HVAC unit.