Meter assembly
2.
3.
38
Insert angled end of hanger blades into the three slots in a hanger hub. When
correctly installed outside hanger blade edges are parallel to hanger hub. The
upstream and downstream edges are perpendicular to hanger hub.
Figure 6-2:
Step 2
Position hanger blades in hanger hub slots to protrude enough from the flat faced
end of the hanger hub to allow the outside edges of hanger blades to fit inside meter
housing bore. Slide assembly, flat faced end first into upstream bore of meter
housing. Push hanger blades so downstream edges are touching deflector ring
upstream edge on rimmed rotor meters or touching upstream edge of step in bore
on rimless rotor meters. Push hanger hub forcing hanger blades outward contacting
meter housing bore. Tap upstream edges of hanger blades with a soft headed
hammer making sure they are properly positioned. Then strike the upstream end of
hanger hub wedging and locking assembly in place.