Commissioning; Start-Up & Shut Down; Start-Up - Afore HNS7000TL Installation And Operation Manual

On-grid pv inverter
Hide thumbs Also See for HNS7000TL:
Table of Contents

Advertisement

6. Commissioning

Before starting up commissioning at site, please make sure below procedures
and requirements are fully meet.
• Mounting location is meet the requirements.
• All of the electrical wiring is firmly connected, including PV wiring, Grid wiring
and Earth wiring.
• The inverter setting has been finished accordingly to local standards or
regulations.
Commissioning Procedures
• Turn on the AC switch between inverter output and the public grid;
• Turn on the DC switch on the inverter;
• Turn on the PV switch of the system.
7. Start-up & Shut Down
Please check the following requirements before testing:
• Installation location is suitable according to Chapter 3.1.3.
• All electrical wires are connected tightly, including PV modules, AC side, Earth
Line.
• Inverters should be set according to the required local grid standard.
• More information please contact with Afore or distributors.

7.1 Start-up

• Turn on the AC switch between the inverter and the public grid.
• Turn on the DC switch between PV panels and the inverter (if any).
• Turn on the DC switch on the inverter.
Inverter will enter into standby mode, and the LCD screen lights up and show
contents , and then complete the first setting of the inverter according to 5.3.1.
The LED will be lighted up after the inverter enter into running states.
Commissioning
22