Commissioning

6.1

Function check

Make sure that all final checks have been completed before you start up your measuring point:
• Checklist "Post-installation check" (see Page 21 ff.).
• Checklist "Post-connection check" (see Page 21 ff.).
6.2

Switching on the measuring device

When the instrument is switched on for the first time, the following messages appear on the display:
After 5 s, the following message appears
After 5 s, the following message appears (e.g. on HART
devices)
After 5 s or after you have pressed
message appears
Select the language
(this message appears the first time the instrument is
switched on)
Select the basic unit
(this message appears the first time the instrument is
switched on)
The current measured value is displayed
F
After
is pressed, you reach the group selection.
This selection enables you to perform the basic setup
Commissioning
F
the following
51

Advertisement

Table of Contents
loading
Need help?

Need help?

Do you have a question about the Fieldbus Levelflex M FMP41C and is the answer not in the manual?

Questions and answers

Subscribe to Our Youtube Channel

Table of Contents