12 | NETWORK INSTALLATION | GEOKON
Power Source
Mains or solar with external battery
Solar without external battery
TABLE 6: Cellular Gateway Supervisor Battery Switch Options
FIGURE 13: Cellular Gateway Supervisor Battery Switch
FIGURE 14: Non-Cellular Supervisor Battery Switch
■
Non-cellular Supervisors 890X-XX-SUP-232, 890X-XX-SUP-USB
Move the battery select switch to either the
depending on the type of battery being used.
Align the positive (+) side of the batteries with the + indicator in the battery
holder. Push the batteries straight down into the holder.
FIGURE 15: Battery Detail
3.2.3 SEAL THE SUPERVISOR
1.
Place the supplied desiccant packs inside the enclosure.
2.
Ensure the cover gasket and the mating ridge on the enclosure are clean,
and that the gasket is properly seated inside the groove on the cover. Place
the cover on the unit.
Geographic Zone
Temperate
Sub Polar
BATTERY
or
ALKALINE
LITHIUM
6:
9-24V
N/A
13:
14:
position
15: