5. OPERATION
5.1. RECOMMANDATIONS
➢ Open the general water tap, if it is closed, then open the water shutoff valve dedicated to the
machine.
➢ Do not put the supplying voltage at this moment.
➢ Verify the presence of water, by reading the pressure of the mains water inlet on the M2
manometer pump.
5.2. INITIAL FILLING
➢ Ensure that steam taps operating levers 'V' are open (up).
➢ Put the ON/OFF switch 'C' to position 1 (power on).
➢ The key board turn on.
➢ The boiler fills automatically, without heating.
➢ The machine start to heat automatically, only when the level probe is reached by the water
➢ A scrolling LED on keypads can inform the user about the status.
➢ Close the steam tap "V" and wait.
➢ When the scrolling leds stops : The machine is ready to operate
5.3. FURTHER FILLINGS
Further fillings will run automatically, according to the hot water needs.
➢
The water level in the boiler is controlled by the electronics, by the means of a level probe.
➢
SACOME, CONFIDENTIAL Document, it is forbidden to duplicate or communicate this document without previous authorization.
Edition 05/2021 - COMPACT - technical documentation - page 6
Need help?
Do you have a question about the COMPACT and is the answer not in the manual?
Questions and answers