2. INSTALLATION

Inspecting Your Shipment

When you receive the shipment of your switch, check the package
contents and make sure you have the following items:
VH-2402S2 stackable switch
Mounting ears and mounting screws
Four rubber feet
ESD wrist strap
Power cord
Product documentation

Site Requirements

Before you install the switch, make sure the site meets the following
requirements:
Mounting
Provide a flat table, shelf surface, or an optional 19 in. (48.3 cm)
equipment rack.
Use an EIA standard equipment rack that is grounded and physically
secure.
Power source
Provide a power source within six feet (1.8 m) of the installation
location. This source must provide 100 VAC to 240 VAC, at 50 Hz to
60 Hz, for 80 VA minimum power. Power specifications for the switch
are shown in Appendix A, "Technical Specifications.
9033819-02
NOTE: One 32 cm stack interconnection cable is
included with every optional Stacking Module.
NOTE: Primary voltage selection within the above
ranges is automatic and requires no user action.