SECTION 4 - MACHINE OPERATION
ALLOW ENGINE TO WARM-UP FOR A FEW MINUTES AT LOW SPEED BEFORE APPLYING
ANY LOAD.
4. After engine has had sufficient time to warm up, shut engine
off.
5. Turn Platform/Ground Select switch to the
Platform position.
6. From the Platform, pull the Power/Emergency
Stop switch out.
7. Push the Engine Start switch until engine
starts.
NOTE:
Footswitch must be in released (up) position before starter will
operate. If starter operates with footswitch in the depressed posi-
tion, DO NOT OPERATE MACHINE.
4-8
Shutdown Procedure
IF AN ENGINE MALFUNCTION CAUSES AN UNSCHEDULED SHUTDOWN, DETERMINE
THE CAUSE AND CORRECT IT BEFORE RESTARTING THE ENGINE.
1. Remove all load and allow engine to operate at low speed
for 3-5 minutes; this allows further reduction of internal
engine temperature.
2. Push Power/Emergency Stop switch in.
3. Turn key of Platform/Ground Select switch to
the Off position.
Refer to Engine Manufacturer's manual for detailed
information.