EM-PMI375
Storage, installation and maintenance checklists
Electric machine weekly maintenance checklist (continued)
Functioning of the cooling system in
general
Notes:
Electric machine and customer information
Customer:
Customer reference:
Service reference:
Electric machine monthly maintenance checklist
General construction
Noise or vibration during operation
in general
Cleanliness of the enclosure and
connected parts
Electrical system
Weariness of the cables
Insulation resistance
(If the electric machine is in
continuous use, it is recommended
to do the insulation resistance test
every three or four months.)
Encoder mounting
Cooling system
Functioning of the cooling system in
general
Tightness of the ventilation plug
©
Danfoss | November 2021
N.A
Electric machine monthly maintenance checklist
Date:
N.A = Procedure not applicable PASS = Procedure passed FAIL = Procedure failed
N.A
PASS
Electric machine type (from the rating plate):
Electric machine serial number:
Date installed:
PASS
FAIL
FAIL