Electrical connections

The device must have been installed before the electrical cables are connected. The supply
power must be switched off.
Once the steps described below have been completed, the device is ready to be put into
operation.
Fig. 12
1 Socket for LCI adapter
2 Analog output 0/4 ... 20 mA (electrically isolated)
3 Power supply 24 V AC/DC
1. A shielded, four-core cable (e.g., 4 x 1 mm
2. Release the four screws on the connection head cover of the flowmeter sensor and remove
the cover.
3. Connect the four cores to the terminals of the flowmeter sensor electronics.
NOTICE - Potential damage to parts!
Electrical isolation is only ensured if terminal 4 is not connected to terminal 2 of the supply
power.
4. Attach the shielding to the EMC cable entry.
IMPORTANT (NOTE)
If the shielding is routed directly into the housing, it will not have the desired effect (shielding
effect will be lost).
5. Attach the connection head cover and screw it tight.
6. Check that the gasket is seated properly.
CI/FMT400-VTS/VTCS-X1
1
4 Terminals
5 Ground
6 Cable entry
Sensyflow FMT400-VTS, FMT400-VTCS
2
3
4
5
2
) must be used to connect the flowmeter sensor.
Electrical connections
6
G00823