Figure A8-16 Failed QAP results

Result History

After QAP is complete, the system generates a test summary page. The result summary table contains
descriptive names, measured values, test specifications (LSL and/or USL) and pass/fail status.
A minimum of 25 QAP test results are maintained.
Follow this process to view the results of previous QAP tests.
1. From the left pane, press [RESULT HISTORY].
The Result History screen appears.
2. Press a test entry in the list to select it.
3. Press [SELECT].
The test details appear.
Figure A8-17 QAP Result History screen