Commissioning
4 Commissioning
CAUTION : HOT SURFACES, DO NOT TOUCH!
- This warning indicates be careful of hot surfaces when operating the product.
- Do not perform any task until the product cool down sufficiently.

4.1 Display Introduction

M88 series include a 4x20 character type LCD display and 2 LED lights
( located on the left-hand side of the LCD ) to indicate inverter's status as shown
in Figure 4-1. Please refer to Table 4-1 for more information about inverter's
statuses and LED indicator.
The following section will introduce the functions that can be adjusted by users
through the LCD panel. When you are adjusting settings, LCD panel will change
the display cursor from "►" to "
Power meter / String monitoring
Energy Log
Event Log
Inverter Information
General Settings
Install Settings
Active/Reactive Power
FRT
According to ERDF certification in France, any production installation with Pmax
power greater than or equal to 5MW shall remain P(F) control and FRT function
in operation.
" .
4.3
4.4
4.5
4.6
4.7
4.8
4.9
4.10
ATTENTION
44