24. START-UP / COMMISSIONING SHEET

THIS EQUIPMENT HAS BEEN FACTORY FIRED AND TESTED PRIOR TO
SHIPMENT. HOWEVER, THIS APPLIANCE IS NOT "PLUG & PLAY". IT RE-
QUIRES COMMISSIONING AND FIELD ADJUSTMENT / SPECIFICATIONS
CONFIRMATION TO ENSURE SAFE AND EFFICIENT OPERATION.
COMMISSIONING REPORT
AS PER I&O MANUAL AND LOCAL/NATIONAL CODES
CONTRACTOR:
STREET:
CITY:
PHONE:
JOBE NAME:
CITY:
HEATER MODEL NUMBER :
Located on burner rating
HEATER SERIAL NUMBER :
Located on burner rating
TO ENSURE THAT SITE CONDITIONS ARE COMPATIBLE WITH THE HEATER'S PER-
FORMANCE AND TO ALLEVIATE NUISANCE CALL-BACKS, THE COMMISSIONING RE-
PORT (next page) NEEDS TO BE COMPLETED BY THE QUALIFIED GAS INSTALLER.
A CALL FOR TECHNICAL SUPPORT MUST PROVIDE THE INFORMATION FROM THE
COMPLETED COMMISSIONING REPORT ON THE NEXT PAGE
TECHNICAL SERVICES:
FAX 1-866-361-0523,
VOICE 1-877-446-3727
WARNING
During start up, material coatings used in the production process of tubes and reflectors will
"burn off" and create smoke during the first hour of operation. This is temporary and normal.
Please ensure that there is sufficient ventilation to adequately clear the smoke from the space.
Notify site and safety personnel to ensure that alarm systems are not unduly activated.
SPW2, STW2(S) / IWP2, IW2(S) I&O Manual
IM170629
RL: 03C
RD: APR 2019
STATE/PROV:
STATE/PROV:
START UP 'SMOKE'
48
CELL:
ZIP: