Fig. 3-8
shows the installation procedure for the external wiring and piping box. The procedure is the same in
RH-3FH/6FH/12FH/20FH. Remove the No. 2 arm cover B and install this option using the same screw holes. The
installation procedure is shown below.
Turn the controller's power OFF before this operation. Refer to
removing/ installing the cover.
1) Remove the each fixing screws and remove the No. 2 arm cover U and the No. 2 arm cover B.
2) Pull out the air hoses or cables from the opening which removed the No. 2 arm cover B.
3) Fix (or connect) the air hoses and cables to this option box.
Previously adjust the air hose and cables to an appropriate length. Make sure that the wiring and piping lines
avoid the side of the J2 reducer (because gap is narrow, it interfere with the No. 2 arm cover U).
Connect the air hoses with the joint inside this option box.
Remove the blind plug attached to this option box and fix the cable with the cable clamp.
To the inside of a robot arm
ロボットアーム内へ
External wiring
and piping box
外部配線配管
(this option box)
ボックス
Cable to pull out
引出すケーブル
(hand output cable, etc.)
 (ハンド出力ケーブルなど)
Fig.3-9 : Fixing the Cable
4) Fix the air hoses and cables to the hole inside of this box by using the attached cable tie. (section <e> of
Fig.
3-8)
Note) Be sure to fix the air hoses and cables to prevent the hoses falling out and breaking the cable. Also,
fix carefully so that the air hose and cables may not be pulled too much.
5) Install securely the external wiring and piping box to the screw holes that previously installed the No. 2 arm
cover B by attached screw. (tightening torque: 1.39 to 1.89Nm).
When installing pull it little by little from the No. 2 arm side, making sure that the air hose and cables are not
bent or trapped.
6) Make sure that the wiring and piping lines on the No.2 arm avoid the side of the J2 reducer (because gap is
narrow, it interfere with the No. 2 arm cover U).
Fix the hoses and cables to the hole shown in section <f> of
located left and right.
7) If the cables and the air hoses have excess length, please tie the excess section using cable tie.
8) Install securely the No.2 arm cover U as before with fixing screws (tightening torque: 1.39 to 1.89 Nm).
Note) The installation surface of the clean and the oil-mist specification covers is using sealing material.
In the event that the sealing material has been removed or has been bent or broken to the extent
that it cannot be return to the original form, be sure to replace the sealing material. Please contact
dealer when the sealing material needs to be replaced.
This completes installing the External Wiring and Piping Box.
Lock nut
ロックナット
Cable clamp
ケーブルクランプ
(Attached to a hand output
cable and a hand input
cable)
3Installing the option devices
Page 68, "5.3.2 Installing/removing the cover"
Fig. 3-8
using cable tie. There are 2 holes,
External Wiring and Piping Box 3-61
for

Advertisement

loading

This manual is also suitable for:

Rh-6fh seriesRh-12fh seriesRh-20fh series