Page 1
PRESENTED BY JPBOWLIN.COM 817.332.8116 J.P. Bowlin is a quality-driven Calibration Company that has provided calibration, repair and sales of all types of weighing and measurement products since 1931.
Any repairs must be performed by B-TEK Scales authorized service technicians. Failure to comply with this policy voids all implied and/or written warranties. General safety warnings are as follows: ...
Before Installation Prior to installation verify the following: The scale design will meet the customer’s application correctly The scale is located so that vehicles can enter and exit easily There will be sufficient drainage of water from the scale area ...
Choosing a Site The first step in installing the scale is to choose an appropriate site. Pertinent steps in choosing the site are: - Ensure that the site has adequate approaching / exiting distance to comply with state and local Weights and Measures regulations. Scale length and scale elevation (maximum fall per foot allowance) will impact the total area requirement.
Page 7
- Check all state and local Weights and Measures requirements before breaking ground to ensure compliance with all regulations. - Obtain all necessary permits for construction. - Check all public utilities to ensure that your site is free of underground lines, pipes or hoses.
- The base plates, which support the load cells, are designed to be anchored to the foundation (or pier) by using expansion bolts placed in concrete after curing. - B-TEK Scales recommends the use of 3/4” X 7” length expansion bolts, which provide greater flexibility, to ensure proper positioning of the scale.
Unpacking Unload the shipping crate of scale components prior to unloading scale platform modules from the truck to verify you have everything included on the packing list. Open all boxes for individual equipment pieces and perform a physical inspection to be certain all components are present and have not been damaged during shipping.
Page 12
Note that the foundation base plates will be a combination of basic plates and combination plates that have the checking assemblies included as shown below. BASIC BASE PLATE COMBINATION BASE PLATE with SIDE CHECKING (four per scale)
Page 13
For each load cell in the scale, a load cell mount kit will be provided. It consists of the following: Lower receiver Upper Receiver 1/8” thick ring plate (2) 1/16” thick shim plates Isolation disc ...
Page 14
It is recommended to layout all foundation base plates prior to permanently anchoring to the foundation. Set the foundation plates in place. Do not secure the plates to the foundation at this time. Ensure that the foundation base plates are all level with each other. Shim plates for use on the top of the foundation base plates are included.
Locating Plate Secure the load cell locating plates to the foundation base plates using the included hex head bolts (2) M12 X 40mm and (1) M8 X 40mm, lock nuts and flat washers. Starting with the first 4-cell module locating plates, place a dummy load cell assembly into the base ring of each locating plate.
Module Assembly (if required) The individual weighbridge modules may have been specified to be shipped to the installation site already assembled. If not, they must be bolted together prior to being placed into / onto the foundation. In addition, if not pre-assembled at the factory the conduit will have to be placed in the module prior to installation.
Page 17
Module Assembly (continued) The left and right halves of weighbridge modules will be bolted together through their respective connection plates. Be sure that the modules being bolted together are matching pairs and have the same type of load cell support ends. First insert (2) 1/2”-13 X 2-1/2”...
Page 18
steel deck connection plates top view of concrete deck connection plates...
Conduit Installation If not ordered as pre-assembled at the factory, the conduit for cable runs must be installed in the weighbridge. The lengths of conduit will be bundled together with your “scale package” and can be inserted thru the lifting lugs located on the inside of either of the module halves.
Center Deck Panel and Clip Installation Steel deck Centurions, 11’ and wide utilizes center deck panels between the left and right connected halves. These cover plates are secured by use of a deck panel clip (#100-60084) and cap screw (#HW-B-1/2-13X1.5SHCS) which are tightened against a panel tube inside the scale module.
Lifting Modules into Place Note: If the scale is a concrete deck version, refer to the following sections for shoring and crowning instructions prior to lifting the modules into place. The first module to be placed onto the foundation is a 4-cell module which should be placed directly after the end wall.
Page 22
Prior to installing the weighbridge module onto the dummy load cell stands ensure that safety supports such as wood blocking is placed under the weighbridge module being lifted. Lift the 4-cell module over the four dummy cell stand assemblies and slowly lower the module so that the button on top of each dummy stand is inserted into the thru hole located in the module’s load cell nest.
Page 23
CORRECT WRONG LOAD CELL / DUMMY STAND ALIGNMENT Take a measurement from the outside edge to the end wall on both sides of the module end plate to ensure that the module is parallel with the end wall. The measurements should be within 1/8” of each other. If they are not, lift and adjust the module to achieve squareness.
Connecting Modules With the first 4-cell module in place you can now lift the next adjoining module into place and attach using the load cell nest brackets. This will be a 2-cell module which consists of upper connection brackets on one end, and load cell connector brackets on the other.
Page 25
Lower the module into place so that the connection shelves rest on top of the 4-cell module’s load cell nests. Lower the opposite end of the module so that the button on top of each stand is inserted into the thru hole located in the module’s load cell nest. LOAD CELL NEST UPPER CONNECTION SHELF...
Page 26
Adjust the 7/8” X 3” bolts that run lengthwise with the scale so that the distance between the end module plates is 9-3/4”. This measurement should be taken on both side of the modules to ensure that the cover plates will fit between the modules properly. As a reference, you need approximately 10-3/4”...
Page 27
Each subsequent 2-cell module, if used, will be installed identical to the module in the previous section, with the load cell nest upper connection bracket mating with the load cell nest lower connection bracket of the adjacent module, with the opposite end of the module resting on dummy load cell stands.
Page 28
Typical installation order of individual Centurion modules 1) 4-cell module starting at end wall location 2) 2-cell modules rest on load cell nest of first module and two cells opposite end 3) Additional 2-cell modules installed identical to the second module...
Approximately 24,000 lbs. of concrete will be poured into a typical 24’ x 11’ B -TEK Centurion weighbridge module. If you have questions about the shoring procedure, please call B-TEK scales at 800-266-8900. The standard B-TEK Centurion concrete deck scale has approximately 6” of clearance from the bottom of the main structural beams to the top of the foundation floor.
Page 30
Shims (metal or wood) will be required to achieve proper elevation of the wood timber. Additional shims can be used in the center of the module to create a positive crown. Refer to the following section in the manual regarding crowning the scale module.
Page 31
Crowning Instructions Once the modules are in place and supported on dummy load cell stands or load cell stands, you must verify that there is a positive crown in the modules. This is to ensure proper rain and snow runoff. The same shoring timbers used for the bottom pan support can be used for crowning the module.
Adjusting the Checking Once assembled, verify that the scale is centered in the foundation. If it is not, make the appropriate adjustments. With the modules bolted together, adjust the end bumper checking and the side checking stands. The poly bumpers on the end wall, and the bolt heads on the side checking stands should be approximately 1/16”-1/8”...
Replacing the Dummy Load Cell Stands Once the end and side checking has been adjusted the dummy load cell stands will need to be removed and replaced with the actual load cells. It is imperative that the checking has been adjusted to minimize the lateral movement of the weighbridges when replacing the stands.
Page 34
Once the dummy load cell stand has been removed, replace with the load cell Assembly per the diagram below: Start by placing the ceramic isolation disc into the circular ring which is part of the locating plate. The load cell bottom cup is then placed inside the isolation disc, with the anti-rotation pin insert into the cup’s blind hole.
Checking the Alignment of Load Cells Once the load cell assembly has been installed it must be checked for correct alignment. Using the B-TEK load cell surface level, supplied to authorized dealers, attach to the lower diameter of the load cell using the integral magnet. The magnet can be adjusted in and out by turning the set screw.
Page 36
Once the entire scale has had the load cell assemblies installed and aligned correctly, readjust all bumper checking assemblies to within 1/16” - 1/8”. At this time drill and install all of the anchors for the base plates. Anchors are sug- gested to be 3/4”...
Connect the Grounding Cables Connect the grounding cables from each load cell to the threaded cable stand-off on the weighbridge. Additionally, connect a grounding cable from the M8 bolt/nut on the locating plate to the same stand-off on the weighbridge. Adjacent weighbridges require an additional grounding wire from the threaded stand- off on the weighbridge which is run to a stand-off on the next weighbridge in line.
Page 38
STAND-OFF Weighbridge Stand-Off to Stand-Off Grounding Wires Load Cell and Locating Plate Grounding Wires to Weighbridge Stand-Offs...
Load Cell Cable Wiring At this point all of the load cell cables can be pulled through the installed conduit. As an option and at an additional cost, digital load cell cables can be requested to be pre- wired at the factory when ordering the scale. Depending on your particular type of Centurion, find the correct wiring diagram on the following pages.
Page 40
BUSS BAR Your digital Centurion “scale package” will include all load cell cables, junction box(es), grounding cables, ground rod, 50’ of homerun cable, indicator, printer with printer ca- ble, and surge protection device. Your analog Centurion and hybrid Centurion “scale package” will include all load cell cables, junction box(es), grounding cables, ground rod, and surge protection device.
Page 41
NO CONNECTION TERMINATOR CONNECT CELL 12 CONNECT CELL 11 CONNECT CELL 10 CONNECT CELL 9 CONNECT CELL 8 CONNECT CELL 7 NO CONNECTION FROM CELL 7 J-BOX 1 NO CONNECTION NO CONNECTION NO CONNECTION TERMINATOR NO CONNECTION TO INPUT J-BOX 2 CONNECT CELL 10 CONNECT CELL 9 CONNECT CELL 6...
Maintenance 1. Be sure that the scale platform is always free of accumulations underneath such as ice, dirt / mud and debris. 2. Inspect the load cell cables for damage. 3. The load cell bearing cups should be inspected, cleaned and greased periodically. 4.
Spare Parts Scale Part Number Item Location HW-B-7/8-9X3 7/8”-9 X 3” L hex bolt Connection of module halves HW-N-7/8-9H 7/8”-9 hex nut Connection of module halves HW-W-7/8L 7/8” lock washer Connection for module halves HW-B-1/2-13X2.5 1/2”-13 X 2-1/2” L hex bolt Connection of module halves HW-N-1/2-13H 1/2”-13 hex nut...
Page 45
Spare Parts Load Cells Part Number Item Location 899-100026 Load cell level (leveling tool) For checking alignment of load cells 899-500000 75K CPD-M digital load cell Load cell mount assembly 899-500002 100K CPD-M digital load cell Load cell mount assembly 899-500004 75K CPR-M analog load cell Load cell mount assembly...
Need help?
Do you have a question about the Centurion-DT and is the answer not in the manual?
Questions and answers