Installation
4
Installation
4.1
General installation procedure
Preliminary requirements
Procedure
1. Unpack the EVSE. Refer to section 4.2.
2. Prepare the site. Refer to chapter 5.
3. Remove the cabinet cover. Refer to section 9.1.
4. Do the mechanical installation. Refer to section 6.1.
5. Do the electrical installation. Refer to section 7.1.
6. Install the cabinet cover. Refer to section 9.2.
7. Do the commissioning procedure. Refer to section 8.1.
4.2
Unpack the EVSE
1. Open the box.
2. Remove the EVSE from the box.
3. Remove all packaging material from the EVSE.
4. Discard the packaging material. Refer to section 3.8.
5. Make sure that all parts are delivered according to the order. Refer to the order
and section 11.6.
6. Do an inspection of the EVSE and the parts for installation for damage.
7. If you find damage or the parts are not according to the order, contact the local
representative of the manufacturer (ABB EV Infrastructure). Refer to section
1.12.
34
1.
All required permits to
agree with the local rules
are granted.
2.
The AC input cable is
available.
•
Tools for installation. Refer
to section 11.7.
•
There is no voltage on the
AC input cable during the
complete installation
procedure.
BCM.V3Y01.0-EN | 002