3.2.2
Examples of installing units using earthquake-proofing
construction methods
This section shows the locations of the anchoring elements used when installing units
by using the earthquake-proofing construction method.
(1) Example of installing a PRIMEQUEST 480/440 system
Figure 3.3 Example of installing a PRIMEQUEST 480/440 system by using
C122-H001-02EN
738 (29.1)
29
680 (26.8)
(1.1)
A
A
PRIMEQUEST
480/440 main unit
40
99
(1.6)
(3.9)
600 (23.6)
Front of unit
the earthquake-proofing construction method
3.2 Earthquake Preparedness Measures
29
(1.1)
99 (3.9)
40
(1.6)
Unit: mm (in.)
3-5