Commissioning - TESY EVHP Series Manual

Domestic hot water heat pump
Table of Contents

Advertisement

6. COMMISSIONING

WARNING! Check that the equipment is
connected to the earth cable.
WARNING! Check that the line voltage
corresponds to that indicated on the
equipment identification plate.
The commissioning procedure must be carried out by
performing the following procedures:
Fill the boiler by acting on the water inlet tap and
check that there are no leaks from gaskets and
connections. Tighten the bolts or connections where
necessary;
Do not exceed the maximum permitted pressure
indicated in the "general technical data" section;
Check that the water circuit safety equipment is
working;
Connect the plug to the power socket;
When the plug is inserted, the boiler is in standby, the
display remains switched off, the power key is
illuminated;
Press the power key (see paragraph 7.1.3.1), the
equipment starts up in the "ECO" mode (default
setting) 5 minutes after pressing the key.
Page 14 of 28

Hide quick links:

Advertisement

Table of Contents
loading

This manual is also suitable for:

Evhp 7s 260 60Evhp 7s 200 60Evhp 260 60Evhp 200 60

Table of Contents