RJ45 terminal pin assignment
PIN
Assignment for inverter scapable of both charging and discharging
1
2
3
4
5
6
7
8
Method of asserting demand response modes
RJ 45 socket asserted
MODE
by shorting pins
DRM0
5
6
DRM5
1
5
DRM6
2
5
DRM7
3
5
DRM8
4
5
31
Chart 5.41
DRM5
DRM6
DRM7
DRM8
RefGen
COM/DRM0
/
/
Requirement
Operate the disconnection device
Do not generate power
Do not generate at more than 50% of
rated power
Do not generate at more than 75% of
rated power and sink reactive power if
capable
Increase power generation (subject to
constraints from other active DRMs)
Note:
For UK:This equipment is equipped with RJ45 terminal for logic interface that
being received the signal from the DNO, the connection should be installed per
installation manual, and the signal should be a simple binary output that captured
by RJ45 terminal( PIN 5 and 1 for detecting the signal). Once the signal actived, the
inverter will reduce its active power to zero within 5s.
Note:
If the cable such as "NTC" (lead-acid battery temperature sensor) cable is not
used, please do not remove the filler plug from the cable support sleeve.

5.5.9 Connection of temperature probe for lead-acid battery

When customer using lead-acid battery, the temperature probe of the lead-acid
battery is used to detect the ambient temperature of the lead-acid battery, the
battery temperature cable of the SPH side connection steps are as follows:
1.Unscrew the swivel nut from the cable gland.
2.Thread the swivel nut over the "NTC" cable.
3.Press the cable support sleeve out of the cable gland.
4.Remove the filler plug from the cable support sleeve.
5.Route the "NTC" cable through a min opening in the cable support sleeve.
6.Thread the "NTC" cable through the cable gland.
7.Insert the RJ45 plug of the network cable into the "NTC" pin connector on the
inverter until it snaps into place.
8.If no other cables need to be installed, lock the waterproof cover to the inverter
with screws.
9.Screw the swivel nut onto the waterproof cover.
Chart 5.42