VERITAS 2U12 Hardware Service Procedure page 6

Shelf

Advertisement

3
Slide the power supply into the slot complete. The power supply clicks when it is properly installed.
4
Plug the power cable into the power supply.
5
Turn on the power supply switch. Verify that the LED on the replacement power supply is green
and that the air flows from the power supply.
HSP 159: Power supply replacement: Veritas 2U12 Storage Shelf