Load the wire rope hoist multiple times (max. load). The following is recommended:
– Load and hold 5 times; each holding phase should last at least one minute.
– The result of the load is a rope that is firmly drawn into the rope bag.
Check the protruding end of the rope wedge.
– Maximum value per "x" (see table).
Check dimension "a" and "b" during annual maintenance.
– To ensure the rope does not slip out of the rope bag.
– With deviations, assemble the rope again as described.
Rope Ø
Part number
[in]
0.354
A70009035
0.492
A70009036
L
a
b
x
[in]
5.9
0.98
0.98
0.24
5.9
0.98
0.98
0.39
Tightening torque
[lb
ft]
f
15
30