Yale HOISTS SHAW-BOX YKA Operation & Service Manual page 73

Wire rope hoists
Table of Contents

Advertisement

4
Installation
(1)
Rope bag
(2)
Rope wedge
(3)
Rope clamp
(4)
Cotter pin
(5)
Rope
07.2020
Rope fastening point (YKA/SKA - YKE/SKE) with special ropes
Procedure only for ropes listed in the table
Rope Ø
[in]
0.354
0.492
see works certificate.
*)
Fig. 45
Clean the rope (5) in the area of the rope anchorage.
– The area must be clear of grease.
Clean the rope bag (1) and rope wedge (2).
– The rope bag (1) and rope wedge (2) must be clear of grease.
Feed the rope end through the rope bag (1) (see figure).
Lay rope (4) around the rope wedge (2) and draw together in the rope bag (1).
– The rope end must protrude out of the rope bag (1) by length "L" (see table).
Secure rope end with rope clamps away from the rope bag at the specified points.
The rope clamp must not be mounted at the rope binding. Secure.
– For dimension "a" and "b" and the tightening torque, refer to the table.
Assemble the rope bag at the fastening point.
– Observe the indicating label on the rope fastening point and the section Position
of the rope fastening point.
Secure with a cotter pin.
– The cotter pin must always be replaced after disassembly.
Part number
*)
A70009035
A70009036
73