5. Loosely install three bolts and nuts securing the
cradle to the UHT transmission that was not servic-
ed. The floor jack might have to be repositioned to
align holes (Fig. 358).
Fig. 358
7. On the side of the machine being serviced, tighten
the 3 bolts and nuts securing the cradle to the UHT
transmission and the 2 bolts securing the UHT
transmission to the frame, torque the nuts and bolts
to 75 ± 8 ft-lbs. (101.7 ± 10.8 Nm) (Fig. 359).
B
A
Fig. 359
A. Cradle to UHT nuts
B. UHT mounted frame bolts
Toro Z Master G3 3000/5000/6000 Series Service Manual
DSCN-4551a
B
A
A
DSCN-4550a
HYDRAULIC SYSTEM
8. Tighten the three bolts and nuts securing the cradle
to the UHT transmission on the side that was not
serviced. Torque them to 75 ± 8 ft-lbs. (101.7 ± 10.8
Nm) (Fig. 360).
Fig. 360
9. Remove the floor jack.
10. Apply thread locking compound to the control arm
bolt (Fig. 361).
Fig. 361
DSCN-4551a
5