Assembly Instructions

Never work under the implement during loading, unloading or installation work. Pay close atten-
tion to safety! The implement is very heavy. Only use lifting devices that have sufficient lifting
capacity. For weight indications, see "5.2 Technical Data" on page 47.
On delivery, the implement may be incompletely assembled in a state that varies with the method
of transport, etc. Use the following assembly instructions as applicable.
2.1

Lifting and unloading

Figure 2.1
Lift the harrow from the front using pallet forks placed under the frame. The lifting positions are
marked with lifting symbols.
Carefully unload the draw-bar, following harrow section and, when applicable, the Crossboard
sections and related parallel rods from the frame. The following harrow thills are packed on a pal-
let.
2.2

Mounting the tines

Figure 2.2
Prior to delivery and to minimise the transport dimensions, all tines on the fifth tine shaft have
been dismantled. To facilitate easy loading and unloading two tines on the third tine shaft have
also been dismantled (this does not apply to the NZA 900 and 1000). The tines are supplied
packed on the frame. Assemble the tines at the indicated positions. The tine brackets should be on
the right of the indications.
NOTE!
Unless the tines are assembled in the correct positions, they may cause damage to the
wheels during transport on the road!