COMMISSIONING AND TESTING

NO SMOKING OR NAKED LIGHTS
The whole installation must be inspected and tested for
soundness and purged up to the gas service cock in
accordance with BS. 6891.
Remove the pressure test point sealing screw on the
burner feed pipe, located at the left hand side of the
control valve, connect a suitable pressure gauge. (See
Fig. 17).
The control tap is marked with the following positions:-
OFF
PILOT ONLY
MINIMUM
MAXIMUM
The stove is fitted with a piezo spark ignitor.
Note: If the main burner or pilot are extinguished for
any reason do not attempt to re-light the pilot for
three minutes.
TO OPERATE THE FAN
Ensure the electricity supply is connected and turned on
press the on button located on the fan control box (see
Fig. 18) this will illuminate the light and the fan should
operate at high speed for approx. 15-20 seconds the light
will go off, the fan speed will reduce and the appliance
can be lit.