Installing Control Cables Between Two Icc Cabinets - Huawei PowerCube 5000 User Manual

Hide thumbs Also See for PowerCube 5000:
Table of Contents

Advertisement

PowerCube 5000
User Manual (SmartLi 100Ah)
Figure 3-36 Installing an AC output cable for the isolation transformer
(1) Site ground bar
A residual leakage protection device needs to be added to the AC device connected to the AC
output of the isolation transformer.
----End

3.7.7 Installing Control Cables Between Two ICC Cabinets

Prerequisites
If two ICC cabinets are deployed, perform the following steps to install cables.
Procedure
Step 1 Install communications cables between ECMs.
Issue 02 (2020-03-17)
Copyright © Huawei Technologies Co., Ltd.
(2) AC output
3 Installation