Power-On Commissioning; Preparing For Power-On; Power-On Mode Of The Icc Cabinet; Powering On The Icc Cabinet Using Pv - Huawei PowerCube 5000 User Manual

Hide thumbs Also See for PowerCube 5000:
Table of Contents

Advertisement

PowerCube 5000
User Manual (SmartLi 100Ah)

5.1 Preparing for Power-On

Step 1 Turn on the battery breaker QF1 in the lithium battery cabinet.
Step 2 Turn on the BCU power switch QS1 in the lithium battery cabinet.
Step 3 (Optional) If there are multiple lithium battery cabinets, repeat the preceding steps.
----End

5.2 Power-On Mode of the ICC Cabinet

5.2.1 Powering On the ICC Cabinet Using PV

Prerequisites
Procedure
Step 1 Check that the PV input, battery, and AC input and output cables are correctly connected.
Step 2 Turn the solar input switch in the ICC cabinet to ON.
Issue 02 (2020-03-17)
5
If the ICC cabinet software needs to be upgraded during the initial site setup, use either of the following
power supply modes to perform the upgrade:
Switch off the battery circuit breaker QF1 in the lithium battery cabinet. Perform the upgrade when
PV power is supplied to each power module in the ICC cabinet.
Turn off the solar input switches of all power modules in the ICC cabinet. Perform the upgrade when
the ICC cabinet is powered by the lithium battery cabinet.
You can perform PV power-on commissioning only when the sunlight is normal.
Check that the PV input voltage is between 200 V DC to 980 V DC.
If the power indicator (green) on the front panel of the HSU is on, the cables are connected correctly. If
the indicator (green) is off, the positive and negative power cables may be reversely connected and need
to be corrected.
Copyright © Huawei Technologies Co., Ltd.

Power-on Commissioning

5 Power-on Commissioning
97