Installing Signal Cables Between Lithium Battery Cabinets - Huawei PowerCube 5000 User Manual

Hide thumbs Also See for PowerCube 5000:
Table of Contents

Advertisement

PowerCube 5000
User Manual (SmartLi 100Ah)
Figure 3-27 Installing AC input power cables for DGs connected in parallel
(1) DG
Step 3 Cover a PVC corrugated pipe over the cable part outside the cabinet and secure the PVC
corrugated pipe to the cable hole.
----End

3.7.3 Installing Signal Cables Between Lithium Battery Cabinets

Prerequisites
Procedure
Step 1 Connect the BCU IN and BCU OUT ports of the BCU in each lithium battery cabinet to form
a loop.
Step 2 Connect the cable on EPO2 in lithium battery cabinet 1 to the cable on EPO1 in battery
cabinet 2.
Step 3 Connect the cable on EPO2 in lithium battery cabinet 2 to the cable on EPO1 in battery
cabinet 3.
Step 4 Remove the existing cable from EPO2 in lithium battery cabinet 3, and connect EPO2 in
lithium battery cabinet 3 to the EPO button contact in lithium battery cabinet 1 using a cable
available in the fitting bag.
Issue 02 (2020-03-17)
In a parallel system, the length and model of the cable between the cabinet and the DGs must be the
same.
Multiple lithium battery cabinets have been configured. This section uses three lithium
battery cabinets connected in parallel as an example.
The number of each lithium battery cabinet is determined by the parallel cable
connection mode. The master cabinet with a display is cabinet 1, the lithium battery
cabinet connected to the BCU_OUT port of cabinet 1 is cabinet 2, and the like.
Copyright © Huawei Technologies Co., Ltd.
3 Installation
78

Hide quick links:

Advertisement

Table of Contents
loading

This manual is also suitable for:

Smartli 100ah

Table of Contents