9.4 Testing New Batteries

For a battery test, please check:
The batteries must be fully charged.
The UPS must be in Normal mode with no active alarms.
Don't take on/off the load.
To test batteries:
1.
Connect the UPS to utility power for at least 48 hours to charge
the batteries.
2.
Press and hold the "I" button 1 second to start the battery test
on line mode or HE mode. The status display string shows
"TEST"