Installation procedure

1.
Prior to the installation of the parts, confirm that the AC input breaker, AC output breaker,
Bypass input breaker and DC breaker are turned off. (De-energize the interior of the UPS.)
2.
Then remove the metal cover plates from UPS.
CAUTION
5.1

Parallel Control Board (TLCR-E*)

Rear side of door
G2020 MMS KIT Installation Manual – 4GBH0111A
Upper left of UPS
Ground bus bar
(Upper)
M4 holes
to connect ground wire

Figure 5-1 Location of ground bus bar (Upper)

CN91 (Lower CN)

Figure 5-2 Location of parallel control board (TLCR-E*)

Example of 750kVA
M3 x 9 holes for spacers
to install parallel control
board (TLCR-E*)