----End

6.2.2 Installing the Rectifier (TP48600B, TP481200B)

Prerequisites
Preparations
Tool: none
Material: rectifier
Skill requirement: skilled technician
Procedure
Step 1 Determining the position of the rectifier
Step 2 (Optional) Remove filler panels from the rectifier installation position based on the
installation requirements.
Step 3 Push the locking latch leftward and pull out the handle.
Step 4 Gently push the rectifier into its slot along the guide rails.
Step 5 Push the handle in place.
Step 6 Push the locking latch downward.
Figure 6-13 Installing the TP48600B rectifier
Issue 02 (2020-01-15)
The pre-fab. modules have been installed.
The rectifier delivered onsite is complete and intact after unpacking and acceptance. If
any problem is found, contact your local Huawei office.
To avoid electric shock, do not put your hands into a rectifier slot.
When a rectifier is running, a high temperature is generated around the air exhaust vent at
the rear. Do not touch the vent or cover the vent with cables or other objects.
Copyright © Huawei Technologies Co., Ltd.