Site Prep Tasks; Selecting The Site; Space Requirements; Dimensions, Weights And Shipping Temperature - Stratasys Fortus 900mc Site Preparation Manual

Hide thumbs Also See for Fortus 900mc:
Table of Contents

Advertisement

SITE PREP TASKS

SELECTING THE SITE

Decide where to install the system based on the following:
1.

Space Requirements

2.
Environmental Requirements
3.
Electrical Requirements
4.
Compressed Air Requirements
5.
LAN Requirements
Note: The 900mc system is capable of generating vibrations depending mainly
on part build geometry and material characteristics. This consideration will need
to be taken into account if locating the system near vibration sensitive equipment.
SPACE REQUIREMENTS

DIMENSIONS, WEIGHTS AND SHIPPING TEMPERATURE

Warning: The system weighs 7247 lbs. (3287 kg) including the crate. Make sure
equipment and personnel are capable of moving the system.
Make sure that the installation site floor space can accommodate the system weight and dimensions (plus
required clearances).
System Size
(uncrated)
System Size
(crated)
System Weight
Shipping Weight
Weight Loading Pads
Operating Altitude
Shipping Temperature Range -40°F to 158°F (-40°C to 70°C)

SEPARATELY SHIPPED ITEM

Kick Panel Box
Width: 109.1 in. (277.1 cm)
Depth: 66.3 in. (168.4 cm)
Height: 79.8 in. (202.7 cm) With light tower attached 89.8 in. (228.1 cm)
Width: 120 in. (304.8 cm)
Depth: 78 in. (198.1 cm)
Height: 88 in. ±1 in. (223.5 cm ± 2.54 cm)
6325 lbs. (2869 kg)
7247 lbs. (3287 kg)
4 pads, each 5.0 x 3.5 inches (12.7 cm x 8.9cm)
Up to 3000m
Note: In freezing temperatures bring the system indoors and leave crated
until the system reaches room temperature.
Width: 65 in. (165.1 cm)
Depth: 37 in. (94 cm)
Height: 34 in. (86.4 cm)
Weight: 278 lbs. (126 kg)