3.1 Switch on/Connecting
System shall be turned on in the correct sequence to avoid any damage.
Step 1: Open cable box outer shell.
___________________________________________________________________
Step 2: Unlock then open Cable box
inner cover. Cable box locker can be
opened without tools.
Step 3: Turn on the PV switch on the
cable box.
Step 4: Turn on the GR switch.
Step 5: If backup load is applied, con-
nect it to Backup ports and turn on the
Backup switch; if not, then keep the
Backup switch off.
NOTE: the Backup switch is only
used when a backup load is applied.